Sewerage Project / Tulkarm

  1. Tulkarem Municipality water supply scheme provides services to the area within the Municipality boundaries in addition  to  the  Nur-Shams Refugee Camp and the newly developed  areas outside the Municipality Boundaries.
  2. The activities of the  project include the identification of the problem, estimation of the exact losses, identification of the required measures to overcome  the water  shortage  within the project area, measures for  proper operation and maintenance of the network, capacity  building   of   the   water   department of the Tulkarem Municipality.
  3. Part of the project activities will be directed towards  the upgrading of  the existing wastewater treatment facilities for the project area and expanding the wastewater collection network to reduce the risk of polluting the water sources.

 

Universal Group in association with DAR
(German Environmental Consultants) performed the following:

  1. Preparation of  detailed   design  drawings and  tender documents.
  2. Define measures to be implemented to reduce the water losses in the Tulkarem Municipality water distribution network.
  3. Design the rehabilitation of the existing  wastewater treatment ponds.
  4. Supervision of the construction works.
Started

Jan 2000

Project Period

30 Months